1.0 OBJECTIVE
To provide standard operating procedure for Distilled Water Transfer Pump.
2.0 SCOPE
Production Department.
3.0 AREA OF OPERATION
Terminal Sterilization Area.
4.0 RESPONSIBILITY
Operator concerned/Production Supervisor.
5.0 ACCOUNTABILITY
Production Executive.
6.0 PROCEDURE
6.1 Check the cleanliness of Distilled Water Transfer Pump & surrounding area.
6.2 Ensure that sufficient Qty. of distilled water in the tank.
6.3 Ensure that sufficient Qty. of dist. water is present in the tank and switch on the main supply.
6.4 Switch on the pump and open the supply valve of the distilled water storage tank after 30 sec. open the distilled water out let valve of the pump.
6.5 Switch OFF the pump after transfer of the distilled water. Close the out let valve of the pump and then supply valve of the distilled water storage tank.
7.0 CLEANING
7.1 Wipe the surface of the pump with dry duster at the end of days work.
8.0 REVIEW DATE
After 2 years or when procedure is changed.
Sunday, July 25, 2010
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment